Dear All,

One of the boiler's burner front wall tubes found corroded.Boiler is
new one and not yet commissioned.Boiler assembled by us.Can I use my
company's or hired welders for a boiler repair constructed by other
company? ASME Authorised Inspector denied our request to utilise our
welders.AI advised us to bring the welders from the manufacturer side
for repair.Which code clause justifying his comment?

Regards,


Limesh

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...