Thursday, January 6, 2011

Re: [MW:9117] Addtional CO2 Service Requirement / Project Specification

Mr.Vino,
Please refer QP Spec QP-STD-R 001 (Rev-01) clause 8.1.7  
 
Regards,
P.Balajirajan.
 
 
-------Original Message-------
 
Date: 1/6/2011 8:47:53 AM
Subject: [MW:9105] Addtional CO2 Service Requirement / Project Specification
 
Dear All,
 
Can you please let me know what are the addtional CO2 Service requirement for Material Selection and how it effects the Material Selection.
Does this requirement(Additional CO2 Sevice) is only for Sour service or this is a General requirement for Material Selection?
 
This requirement is stated in one of the QP Specification for Material for LP Gas Compressor Package.
 
Hope to see your as usual extended co-operation.
 
Regards
Vino P Varghese
Project QA/QC Manager
Doha-Qatar

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
FREE winter Photo Animations for your email – by IncrediMail

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...