Re: [MW:9366] ASME Sec VIII, Div 1, Pressure Vessel/ Dish End

Added add few more points to Mr. Karthik's suggestions in blue font.
 
Thanks,
Dokku Ajay Kumar


From: Karthik <karthik6684@yahoo.com>
To: materials-welding@googlegroups.com
Sent: Fri, January 21, 2011 7:01:17 AM
Subject: Re: [MW:9359] ASME Sec VIII, Div 1, Pressure Vessel/ Dish End

Hi,
Please find below my suggestions as marked in RED.
1) Does this shop need to have ASME "U" Stamp? - No need. (UG-11 (b) )

2) Do we require a Partial Data Report from this Manufacturing Unit duly signed by Autorised Inspector? - No need.Manufacturer of the
part shall furnish identification in accordance with UG-93. PDR would be required if the heads are not in single piece.
You have to certify the Dish end as you are the U stamp holder and manufacturer as per (UG-11 (b) ) and UG-79 and submit the report and related documents to AI for acceptance.

3) Do we require this Manufacturing Unit to be Approved by requesting them to submit Pre-Approval Document? - As per your Quality System.

4) What all min. Documents are required to be submitted in accordance to ASME Sec VIIII Div 1. - If for dish end only means,Material certificates,Dimension Reports,If there is any Heattreatment applicable...Heat treatment report etc.,
If for the Whole vessel,it will be as per your quality manual and ASME Sec.VIII,Div.1-Appendix-10,10-3 (Record Retension)
 
If there is any tack welding to be done on the heads for lifting hooks etc., the vendor has to provide WPS,PQR & WQR as per ASME Sec.IX for approval to you who has the final authority for applying code stamp on vessels. Please refer U 2(B) (2), whcih states that "Some type of work, such as forming, NDE, & heat treatment, may be performed by others (for welding refer UW-26 & UW31). It is the vessel or part manufacturer responsibility to ensure that all work so perfomed complies with all applicable requirment of this division".

 

Refer UW-31 (C) last paragraph, which states that " Provided the work done under the provisoins of U2(b), it is not necessary that a subcontractor making such tack welds for a vessel or parts manufacturer be a holder of a code certificate of Authorization. The requirement oF uw-26(d) do not apply to such tack welds."


5) The Contract for this Vessel was signed by Client on June 2010. Can we use ASME Sec VIIII Div 1, 2007 with 2009 Addenda or we have to follow ASME 2010? - You can use ASME Sec VIIII Div 1, 2007 with 2009 Addenda
 
 
Please do provide relevant Clause from ASME supporting the above Queries.
 
Hope to see as usual opinion. Also someone can share QAP of similar use.(SA 516 Gr. 70 + Clad , Incolloy 825.) and relevant WPS. - You mean ITP? it shall be prepared by you as per the drawing and scope of work.
For WPS..please send the doubts in preparation of WPS.we can assist you.
Thanks & Regards,

(Karthik)

Karthikeyan.S
QA/QC Manager
Getabec Energy Co.,Ltd.
379,Moo6,Soi8,Nikhomphatana,
Rayong-21180,
Thailand.
Phone: 0066 38 897035-8 (Off)
Fax: 0066 38 897034
Hand Phone: 0066 892512282


--- On Fri, 1/21/11, Vino Varghese <vinopvarghese@gmail.com> wrote:

From: Vino Varghese <vinopvarghese@gmail.com>
Subject: [MW:9358] ASME Sec VIII, Div 1, Pressure Vessel/ Dish End
To: materials-welding@googlegroups.com
Date: Friday, January 21, 2011, 2:17 AM

Dear All,
 
We have a Partial Cladded Vessel("U" Stamp Vessel) which we are intend to fabricate at our Manufacturing shop and is designed for Sour Service.
The Overall thickness is 30 mm.
 
The Partial Claddded Area has the -
Base material = 27 mm thickness , SA 516 Gr. 70
Clad Material =  3mm min. , Incolloy 825.
 
One of the Dish End is a Cladded part(Explosion Bond Method) which we are planning to off load work to a "U" Stamp Manufacturer Shop due to limited forming availablity at our Fabrication Facility.
My Question -
1) Does this shop need to have ASME "U" Stamp? - No need. (UG-11 (b) )

2) Do we require a Partial Data Report from this Manufacturing Unit duly signed by Autorised Inspector? - No need.Manufacturer of the
part shall furnish identification in accordance with UG-93.
You have to certify the Dish end as you are the U stamp holder and manufacturer as per
(UG-11 (b) ) and UG-79 and submit the report and related documents to AI for acceptance.

3) Do we require this Manufacturing Unit to be Approved by requesting them to submit Pre-Approval Document? - As per your Quality System.

4) What all min. Documents are required to be submitted in accordance to ASME Sec VIIII Div 1. - If for dish end only means,Material certificates,Dimension Reports,If there is any Heattreatment applicable...Heat treatment report etc.,
If for the Whole vessel,it will be as per your quality manual and ASME Sec.VIII,Div.1-Appendix-10,10-3 (Record Retension)
5) The Contract for this Vessel was signed by Client on June 2010. Can we use ASME Sec VIIII Div 1, 2007 with 2009 Addenda or we have to follow ASME 2010? - You can use ASME Sec VIIII Div 1, 2007 with 2009 Addenda
 
Please do provide relevant Clause from ASME supporting the above Queries.
 
Hope to see as usual opinion. Also someone can share QAP of similar use.(SA 516 Gr. 70 + Clad , Incolloy 825.) and relevant WPS. - You mean ITP? it shall be prepared by you as per the drawing and scope of work.
For WPS..please send the doubts in preparation of WPS.we can assist you.
 
Thanks & Regards
Vino P Varghese
Doha-Qatar

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.